Mark Leung Design

The STEP, Ngau Tam Mei

Transitional housing (new build)
4 storeys; approx. 1,200 modules; approx. 22,000 sq m
The STEP, Ngau Tam Mei
Data & Credits
Client
NT Federation of Associations for Community Services Foundation (operator)
MiC supplier
CIMC Modular Building Systems
Type
Transitional housing (new build)
Area / Storeys
4 storeys; approx. 1,200 modules; approx. 22,000 sq m
Period
01/2024 – 05/2025
Year
2024 – 2026
The STEP, Ngau Tam Mei

Description

At 8 San Sin Road, Ngau Tam Mei, Yuen Long. Funded under the scheme supporting NGOs to deliver transitional housing, HK$682.5M approved. Works began January 2024, completed February 2026, occupation March 2026, operating for not less than five years. Each unit has its own bathroom and cooking space, with barrier-free units provided. Housing Bureau figures: three four-storey residential blocks, a two-storey service building and sewage treatment facilities; 1,208 units in total, about 2,800 residents.

My Role & Responsibilities