Description
At 115 Castle Peak Road – Tsing Lung Tau, Tsuen Wan. A Housing Bureau transitional housing project with HK$48.025M funding. Construction began October 2022, completed end of November 2023, occupied January 2024, built with Modular Integrated Construction. Housing Bureau figures: 85 units (72 one/two-person, 12 two/three-person, 1 barrier-free), about 172 residents.
My Role & Responsibilities
- Modular detailing and module breakdown (joints, MEP embedment)
- Assisting statutory submissions for the MiC scope (Buildings Dept, Fire Services Dept and related)
- Factory follow-up: production, inspection, sample modules
- Site follow-up: transport, lifting, installation, finishing
- Coordinating structural, MEP and facade consultants
- Assisting on cost and programme control (not lead)
- Client and operator liaison