Mark Leung Design

Wellness Lodge, Tsing Lung Tau

Transitional housing (Modular Integrated Construction)
3 storeys; 90 modules; approx. 1,630 sq m
Wellness Lodge, Tsing Lung Tau
Data & Credits
Client
Po Moon Foundation Ltd. (Housing Bureau Transitional Housing Scheme)
MiC supplier
CIMC Modular Building Systems
Type
Transitional housing (Modular Integrated Construction)
Area / Storeys
3 storeys; 90 modules; approx. 1,630 sq m
Period
11/2022 – 01/2024
Year
2022 – 2024
Wellness Lodge, Tsing Lung TauWellness Lodge, Tsing Lung Tau

Description

At 115 Castle Peak Road – Tsing Lung Tau, Tsuen Wan. A Housing Bureau transitional housing project with HK$48.025M funding. Construction began October 2022, completed end of November 2023, occupied January 2024, built with Modular Integrated Construction. Housing Bureau figures: 85 units (72 one/two-person, 12 two/three-person, 1 barrier-free), about 172 residents.